NEW FIRE STATION

  • font sizeA
  • A
  • A

The Rural Municipality of Victoria Beach is proud to announce that together with the generous support of $1,850,500 from the Municipal Economic Development Infrastructure Program (MEDIP) administered by the Province of Manitoba Department of Municipal and Northern Relations, the new RMVB Fire Station project is now complete and the new fire truck will be ready in the summer of 2026. 

Built by LCL Construction LTD







Progress Reports 

27 February 2026 - Final Report 

From LCL:

The Victoria Beach Fire Hall project is complete!  The final walkthrough was completed on February 20.  

Thanks to everyone involved in this project for your hard work and dedication, we couldn’t have done it without all of you!  We should all be very proud to provide this amazing facility to the community of Victoria Beach!
















06 February 2026 - Electrical Commissioning & Start-up, Mechanical Commissioning & Start-up

30 January 2026 - Electrical, Control Wiring, Plumbing










23 January 2026 - Millwork

16 January 2026 - Electrical, HVAC & Hydronic, Control Wiring, Door Slabs & Hardware Install, Plumbing, Specialties, Canopy Roof Framing, Glazing

09 January 2026 - Electrical, HVAC & Hydronic, Door Slabs & Hardware Install, Plumbing, Millwork, Timber Frame Canopy

19 December 2025 - Electrical Shop Rough-in & Piping, HVAC Rough-in, Tile Install, Door Slabs & Hardware Install

12 December 2025 - Electrical Shop Rough-in & Piping, HVAC Rough-in, Painting – Prime & First Coat








05 December 2025 - Electrical Shop Rough-in & Piping, HVAC Rough-in, Wall & Ceiling Drywall & Bulkheads, Mud & Tape, Interior Stair Install, Well Connection

28 November 2025 - Electrical Rough-in & Distribution, HVAC Rough-in, Wall & Ceiling Insulation & Drywall, Mud & Tape, Interior Stair Install

21 November 2025 - Backfilling & Final Grading, Overhead Door Install, Electrical Rough-in & Distribution, Wall & Ceiling Insulation & Drywall








14 November 2025  - Electrical Rough-in & Distribution, Wall & Ceiling Insulation & Drywall

07 November 2025 - Spray Foam Insulation, Concrete Apron Prep, Plumbing Rough-in, Electrical Rough-in & Distribution, Liner Panel Install, Concrete Grinding – Below 2nd Floor & O/H Door Openings, Ceiling Insulation & Drywall



31 October 2025 - Concrete Apron Prep, Spray Foam Insulation, Plumbing Rough-in, Electrical Rough-in, Interior Framing

24 October 2025 - Bollard Installation, Concrete Apron Prep, Spray Foam Insulation, Interior Framing



17 October 2025 - Floor Heat Rough-in, Site Gravel Build-up, Slab Prep & Pour, Eavestrough & Downspouts, Concrete Apron Prep, Spray Foam Insulation

03 October 2025 - Site Gravel Build-up, Slab Prep, Holding Tank, Interior backfill & compaction



26 September 2025 - Raft slab pour, roof/wall cladding, plumbing rough-in

19 September 2025 - Pre-Engineered Building Erection, Raft Slab Prep 



12 September 2025  - Pre-Engineered Building Erection, Raft Slab Prep, Exterior Under-slab Insulation, Exterior Backfill

05 September 2025 - Backfill Exterior, Electrical Conduit Trenching, Pre-Engineered Building Erection



22 August 2025 - Grade beam prep and pour

15 August 2025 - Backfill, grade beam prep

08 August 2025 - Pier prep and pour, backfill

11 July 2025 - Excavation