The Rural Municipality of Victoria Beach is proud to announce that together with the generous support of $1,850,500 from the Municipal Economic Development Infrastructure Program (MEDIP) administered by the Province of Manitoba Department of Municipal and Northern Relations, the new RMVB Fire Station project is now complete and the new fire truck will be ready in the summer of 2026.




Progress Reports
27 February 2026 - Final Report
From LCL:
The Victoria Beach Fire Hall project is complete! The final walkthrough was completed on February 20.
Thanks to everyone involved in this project for your hard work and dedication, we couldn’t have done it without all of you! We should all be very proud to provide this amazing facility to the community of Victoria Beach!







06 February 2026 - Electrical Commissioning & Start-up, Mechanical Commissioning & Start-up
30 January 2026 - Electrical, Control Wiring, Plumbing



12 December 2025 - Electrical Shop Rough-in & Piping, HVAC Rough-in, Painting – Prime & First Coat



14 November 2025 - Electrical Rough-in & Distribution, Wall & Ceiling Insulation & Drywall
24 October 2025 - Bollard Installation, Concrete Apron Prep, Spray Foam Insulation, Interior Framing


03 October 2025 - Site Gravel Build-up, Slab Prep, Holding Tank, Interior backfill & compaction



26 September 2025 - Raft slab pour, roof/wall cladding, plumbing rough-in
19 September 2025 - Pre-Engineered Building Erection, Raft Slab Prep


22 August 2025 - Grade beam prep and pour
15 August 2025 - Backfill, grade beam prep
08 August 2025 - Pier prep and pour, backfill