NEW FIRE STATION

  • font sizeA
  • A
  • A

The Rural Municipality of Victoria Beach is proud to announce that together with the generous support of $1,850,500 from the Municipal Economic Development Infrastructure Program (MEDIP) administered by the Department of Municipal and Northern Relations, the new RMVB Fire Station project is well underway. 

Built by LCL Construction LTD

Progress Reports

24 October 2025 - Bollard Installation, Concrete Apron Prep, Spray Foam Insulation, Interior Framing


17 October 2025 - Floor Heat Rough-in, Site Gravel Build-up, Slab Prep & Pour, Eavestrough & Downspouts, Concrete Apron Prep, Spray Foam Insulation

03 October 2025 - Site Gravel Build-up, Slab Prep, Holding Tank, Interior backfill & compaction


26 September 2025 - Raft slab pour, roof/wall cladding, plumbing rough-in

19 September 2025 - Pre-Engineered Building Erection, Raft Slab Prep 


12 September 2025  - Pre-Engineered Building Erection, Raft Slab Prep, Exterior Under-slab Insulation, Exterior Backfill

05 September 2025 - Backfill Exterior, Electrical Conduit Trenching, Pre-Engineered Building Erection


22 August 2025 - Grade beam prep and pour

15 August 2025 - Backfill, grade beam prep

08 August 2025 - Pier prep and pour, backfill

11 July 2025 - Excavation